Securing ultrapure water supply for pharmaceutical production

With limited space and a narrow window for installation, replacing critical ultrapure water systems at an operational pharmaceutical manufacturing facility required careful planning. Ramboll helped a global pharmaceutical company establish the technical basis for the replacement systems, prepare the project for procurement and provide owner’s engineer services for design review.
For pharmaceutical manufacturers, a reliable supply of ultrapure water is critical to maintaining production. When two ultrapure water systems at a manufacturing facility in Singapore reached the end of their useful life, the client needed to plan their replacement while accommodating the constraints of an existing operational facility.
Space for the new systems was limited, and continuous production meant there was only a short window available to connect the replacement systems to the existing infrastructure.
The project forms part of Ramboll's wider relationship with the global pharmaceutical and consumer products company. Across the client's international manufacturing network, Ramboll provides engineering and technical support for industrial water and wastewater management, enabling knowledge and best practices to be shared across locations.
Finding the right solution within an operational facility
Ramboll began by assessing different location options for the replacement systems, taking into account the limited space available within the existing facility.
Based on the feasibility studies, the team developed the design basis and cost estimate for the project. This work provided the client with technical information to support internal discussions and project funding approvals.
As the project progressed, Ramboll developed the concept design and user requirements for the new systems, bringing together requirements from multiple stakeholders and technical disciplines.
Creating a strong basis for procurement
Ramboll also supported tender management and the technical evaluation of proposals for the new ultrapure water systems.
The design basis, concept design, and user requirements gave vendors and contractors a comprehensive foundation for developing their proposals. As a result, the client received competitive offers and gained greater clarity around project costs and scheduling as the replacement programme moves forward.
RELATED PROJECTS
Strengthening water resilience for a global healthcare manufacturer
Learn more about Strengthening water resilience for a global healthcare manufacturerRamboll assessed water supply risks across 21 production facilities for a global healthcare manufacturer. Starting with a two-site pilot, the team identified where water supply disruptions could interrupt critical production and recommended measures tailored to each site to ensure manufacturing continuity.